ELECTRICIAN 1st YEAR WEEK WISE NSQF SYLLABUS (SPILT UP)

WEEK. NO. 17  & 18

  1. Reference Learning Outcome :-Estimate, Assemble, install and test wiring system. (Mapped NOS: PSS/N6001)
  2. Duration :- Professional Skill 200 Hrs.; Professional Knowledge 42 Hrs.(for above learning out come)
TRADE THEORY (Professional Knowledge ) :- 
    • I.E. rules on electrical wiring.
    • Types of domestic and industrial wirings.
    • Study of wiring accessories e.g. switches, fuses, relays, MCB, ELCB, MCCB etc.
    • Grading of cables and current ratings.
    • Principle of laying out of domestic wiring.
    • Voltage drop concept.
TRADE PRACTICAL (Professional Skills  With Indicative Hours) :- Job no. & Name of the Practical
  • 62. Identify various conduits and different electrical accessories. (8 Hrs.)
  • 63. Practice cutting, threading of different sizes & laying Installations. (17 Hrs.)
  • 64. Prepare test boards / extension boards and mount accessories like lamp holders, various switches, sockets, fuses, relays, MCB, ELCB, MCCB etc. (25 Hrs.)

WEEK. NO. 19, 20  & 21

  1. Reference Learning Outcome :-Estimate, Assemble, install and test wiring system. (Mapped NOS: PSS/N6001)
  2. Duration :- Professional Skill 200 Hrs.; Professional Knowledge 42 Hrs.(for above learning out come)
TRADE THEORY (Professional Knowledge ) :- 
    • PVC conduit and Casing-capping wiring system.
    • Different types of wiring –
    • Power, control, Communication and entertainment wiring.
    • Wiring circuits planning, permissible load in sub-circuit and main circuit.
TRADE PRACTICAL (Professional Skills  With Indicative Hours) :- Job no. & Name of the Practical
  • Electrical Wiring:-
    Prepare drawing of
  • 65. Draw layouts and practice in PVC Casing-capping, Conduit wiring with minimum to more number of points of minimum 15 mtr length. (15 Hrs.)
  • 66. Wire up PVC conduit wiring to control one lamp from two different places. (15 Hrs.)
  • 67. Wire up PVC conduit wiring to control one lamp from three different places. (15 Hrs.)
  • 68. Wire up PVC conduit wiring and practice control of sockets and lamps in different combinations using switching concepts. (15 Hrs.)

WEEK. NO.   22, 23,  24 & 25

    1. Reference Learning Outcome :-Estimate, Assemble, install and test wiring system. (Mapped NOS: PSS/N6001)
    2. Duration :- Professional Skill 200 Hrs.; Professional Knowledge 42 Hrs.(for above learning out come)
TRADE THEORY (Professional Knowledge ) :- 
    • Estimation of load, cable size, bill of material and cost.
    • Inspection and testing of wiring installations.
    • Special wiring circuit e.g. godown, tunnel and workshop etc.
TRADE PRACTICAL (Professional Skills  With Indicative Hours) :- Job no. & Name of the Practical
  • 69. Wire up the consumers main board with MCB & DB’s switch and distribution fuse box. (15 Hrs.)
  • 70. Prepare and mount the energy meter board. (15 Hrs.)
  • 71. Estimate the cost/bill of material for wiring of hostel/ residential building and workshop. (15 Hrs.)
  • 72. Practice wiring of hostel and residential building as per IE rules. (15 Hrs.)
  • 73. Practice wiring of institute and workshop as per IE rules. (15 Hrs.)
  • 74. Practice testing / fault detection of domestic and industrial wiring installation and repair. (15Hrs.)

WEEK. NO. 26 

  1. Reference Learning Outcome :-Plan and prepare Earthing installation. (Mapped NOS: PSS/N6002)
  2. Duration :- Professional Skill 25 Hrs.; Professional Knowledge 07 Hrs.(for above learning out come)
TRADE THEORY (Professional Knowledge ) :- 
    • Importance of Earthing.
    • Plate earthing and pipe earthing methods and IEE regulations.
    • Earth resistance and earth leakage circuit breaker.
TRADE PRACTICAL (Professional Skills  With Indicative Hours) :- Job no. & Name of the Practical
  • 75. Prepare pipe earthing and measure earth resistance by earth tester / megger. (10 Hrs.)
  • 76. Prepare plate earthing and measure earth resistance by earth tester / megger. (10 Hrs.)
  • 77. Test earth leakage by ELCB and relay. (5 Hrs.)